Bromley by Bow, London

Request:

To install parking logs around the perimeter of the car park/service area, so the new fleet of electric delivery vans do not drive too close to the charging points and damage them.

MSL PLanned Maintenance Project installing parking logs

Timescale:

One week

Conclusion:

There was a total of 65 logs to fit with three fixings in each log. With the works being around the service yard and parking areas, there were a number of vehicle deliveries and fork truck movement, so the RAMS had to show this. We also made sure there were no 110-volt leads around the areas. We opted to carry the works out with the use of a generator and worked local to each area completing sections at a time to hand over.