Location

Oldham

Request

To attend site, disconnect existing 10-meter lamp post which had been hit by a lorry, break out around the lamp post, remove and dispose of it then replace with new

Time Scale

This should have been 2 days initially but ended up being 7/8 days

Conclusion

Due to unforeseen circumstances, the client was made aware throughout the works. Our original RAMS had to be changed for a Construction Phase Plan, due to the nature of the job, which had turned into something quite different from the original one, and the types of equipment/plant that was now required to successfully achieve the end result in the lamp post being exchanged for the new one