Location:
Oldham
Request:
To refurbish 2 canteens whilst remaining operational.
- Remove and replace old lighting with new LED
- Replace suspended ceilings
- Reposition all vending machines and associated electrical and water supplies
- Prepare walls and redecorate in corporate colours
- Remove and replace flooring with clients new colour scheme
- Install TV’s and aerials for internal promotional videos
Before:
Time scale:
2 Weeks
Conclusion:
All the works were coordinated and executed to a high standard which were on time and within the budget set for the works. Afterwards the client also mentioned the sentiments of its employees who had started to use the facilities again which gave a feel good factor and improved motivation of staff.
Find out more about our Planned Maintenance Services.
Contact MSL
Call us today on 0333 1234450 or fill out the form on our contact page and we will get back to you.